What are the requirements for the installation of the glass steel desulfurization tower?
Release time:2018-1-28 20:02:49      Click on times:1090
What kind of requirements should be observed in the installation process of the glass steel desulfurization tower?
Flue gas desulfurizer
Note that the diameter of the tower block and the diameter of the tower should be as small as possible. Tower body block assembly connection, FRP desulfurization tower should be paid attention to the gasket circular arc surface and rib root circle of the tower body joint, the shell assembly shall ensure watertight power should have security measures, power cords, caring junction box sealing measures should be taken, to prevent humidity to enter, burn out.
The inlet and outlet pipes can be adjusted according to the actual situation on the site by changing the direction of the screw holes in the flange. The fan shall be installed in the upward draft, and the clearance between the fan blade end and the tower body shall be no more than 100mm, and the four blades shall be adjusted to the same Angle, and ensure that the rotating plane of the impeller is perpendicular to the center line. It is required to install surface level and evenly spaced.
Ensure the pillar and the feed line contact with good foundation, foundation embedded steel plate, glass fiber reinforced plastic desulfurization tower base installation surface profile control and guarantee on the same surface, the pillar and the inlet pipe axis vertical surface. FRP desulfurization tower circulating pump, attention should be paid to the cooling water flow rate and meet, glass steel desulfurization tower cooling tower shall be maintained in the design flow when using + / - 5% range, in case the water is too large, affect the cooling effect.
What are the requirements for the installation of the glass steel desulfurization tower?
1. The glass steel desulfurization tower is concerned to ensure the diameter of the tower block assembly, especially the diameter error of the tower in the tower body of the glass steel desulfurization tower should be minimized.
2. When the glass steel desulphurization tower block is assembled and assembled, the glass steel desulfurization tower should be paid attention to make the gasket arc surface and the tower body ribbed surface, and the lower case assembly should ensure the watertight.
3. There should be safety measures for the power supply of the glass steel desulfurization tower. After the power line is connected, the box should be sealed to prevent moisture entering and burning.
4. The direction of inlet and outlet of glass steel desulfurization tower can be adjusted according to the actual situation on the site by changing the direction of the screw hole on the flange.
5, FRP desulfurization tower fan should be installed into convulsions, upward fan blade tip and the tower body uniform clearance shall be not greater than 100 mm, four blade should be adjusted at the same point of view, and ensure the impeller rotating plane and vertical centerline.
6. The glass steel desulfurization tower requires the surface to be smooth and evenly spaced.
7, FRP desulfurization tower columns under guarantee and the feed line contact with good foundation, foundation embedded steel, glass steel desulfurization tower base installation surface profile control and guarantee on the same surface, the pillar and the inlet pipe axis vertical surface.
8, FRP desulfurization tower circulating pump, attention should be paid to the cooling water flow rate and meet, glass steel desulfurization tower cooling tower shall be maintained in the design flow when using + / - 5% range, in case the water is too large, affect the cooling effect.

The news that you are interested in
Before:Analysis of glass steel desulfurization tower
Next:No more!

Recommended for you

Copyright ©️ 2017 All rights Reserved Shandong Rui Jia Vention Environmental Protection Technology CO,Ltd. Lu ICP No. 17053480
Platform support:上海微领软件    Design and manufacture:徐州网商天下信息科技有限公司